Cold Joint:
A Cold Joint is a plane of weakness
in concrete caused by an interruption or delay in the concreting operations. It
occurs when the first batch of concrete has begun to set before the next batch
is added, so that the two batches do not intermix properly. Sometimes Cold Joints
occur because of emergency interruptions & delays and sometimes because of
the work stoppage at the end of the day, but they can also occur from poor consolidation.
Figure-01 indicates a cross section of a road with cold joint,
Figure-01: Cold Joint
To prevent or avoid Cold Joint in walls,
beams and other structural components it is necessary to place concrete in
layers about 18 inches deep and intermix each layer with the previous one by
using a vibrator. Placement of concrete should begin in the corners and work
toward the center. When slabs are placed the concrete should be placed against
the preceding batch and not dumped in an individual pile. On sloping grades the
work should proceed uphill. In hot weather a retarding admixture may be needed
to slow the setting time.
Cold Joint is simply a joint of concrete
pour which is usually seen in construction field, which will happen naturally for
long length structures with a slope such as long length span of a bridge, long length
slab of a building structures etc.
For Example,
Suppose we have a long span of 38 meter
of a Flyover and we are unable to pour concrete the total span at a time. Now
see the following figure,
Figure-02 which indicates how can Cold Joint forms in concrete in practical life,
Drawing by Engr. Snehashish Bhattacharjee (Tushar), seasoft022.blogspot.com |
Figure-02: Cold Joint forms in concrete (at practically)
Now let’s analyze this Figure-02. From
this Figure-02, there are two Piers and a 38 m span is in between them. The
distance between Pier-A & Pier-B is 38 m. This is a Cast-In-Situ Span. So,
we need to cast this span at site. It is needed to be remembered that there is
a slope between two piers, the slope is downward from Pier-A to Pier-B.
Now, what
will be the concreting process of this Cast-In-Situ span?
At first let’s start our concreting process
from Pier-A. Our destination is to concrete pour up to 13 m from Pier-A. This
13 m is not any fixed distance, actually there is a slope between two Pier
(downward slope from Pier-A to Pier B), that’s why at the time of concreting
when concrete was in liquid state, it behaves like water & wanted to go to downward.
Because of more amount of liquid material will create a free flow & will want to go
downward. It causes the damage/not proper quality of casting process.
So that, we
need to stop at a distance (here is 13 m, just say). Then after casting at Pier-A, now we will go to the
other side at Pier-B, here we will do concreting process at the distance 13 m also from Pier-B.
So, we
have completed concreting process 13 m from Pier-A & 13 m from Pier-B (total
13 m+13 m=26 m), other 12 m (38 m-26 m=12 m) in between is not be filled up yet by
concrete. Now when we re-back to start our concreting process at the last 12 m
space then the new concrete pour will go to create a bond with the concrete
which we have already concreted (26 m). The concreting process which is already completed (13 m
from Pier-A & 13 m from Pier-B) going to be hardened and already become hard
than new concrete pour (12 m space). Here bonding between the new concrete pour
and old concrete pour not be happened properly and create a weak point as a joint
which we have called “Cold Joint”.
Actually Cold Joint is not acceptable in
case of any concreting process. Any Engineer does not like/appreciate Cold Joint, but in
some situation Cold Joint is performed where we can’t do anything.
For Example, in this situation (Figure-02), we have nothing to avoid Cold Joint
because,
---This
is a span with long length so that we could not continue concreting process
simultaneously,
---There
is a slope so that we could not pour the concrete continuously, because concrete
is in liquid state which behaves like water and want to go downward automatically
during concreting time, so quality can’t be maintained properly, so that we
have a distance limitation.
---Here,
It will be helpful for us to do concreting process at last 12 m space because
concreting at the other two sides (Pier-A & Pier-B) have already done &
it become hardened during the last casting process at last 12 m space, so that
concrete could not go anywhere from its own place.
Different types of Cold Joint:
Cold Joint can be forms in concrete in Vertical & Horizontal both direction also,
Figure-03 indicates Vertical Cold Joint forms in concrete,
Figure-03: Vertical Cold Joint
Figure-04 indicates Horizontal Cold Joint forms in concrete,
Figure-04: Horizontal Cold Joint
How can we avoid Vertical and Horizontal Cold Joint:
Assume
that any foundation contractor is not able to pour all of the concrete for a
foundation at once, leaving vertical and horizontal cold joints. They can prepare
the surface of the concrete after the first pour by,
By using epoxy bonding agents named Anti-Hydro mixtures:
---They can
use a concrete additive called Anti-Hydro. It’s available in one-gallon jugs
and five-gallon cans at most builder supply stores for about $13 per gallon.
Mix one part Anti-Hydro to three parts clean water, and add enough fresh (not
old, lumpy, or partially hydrated) Type I Portland cement to make a thick, rich
slurry, or "Slush Coat." Apply this mixture liberally with a stiff
brush to the clean cold joint immediately before you pour. If they are on a big
pour and the slurry has started to set up by the time they get to it, just
brush on more. This will result in a strong, continuous bond.
---Anti-Hydro increases the percentage
of hydration in concrete without affecting its chemical composition, resulting
in a denser, harder, stronger, and more waterproof material. It also
accelerates the rate of hydration, so it has many uses with all Portland
cement-based products.
---There are also many different Epoxy Bonding Agents available from a variety of manufacturers (including
Anti-Hydro). The better quality epoxies are expensive, but are supposed to
provide a joint at least as strong as the concrete.
By using Extra Reinforcement method:
If anyone have extra reinforcement that extends out of the
cold joint 30 to 40 bar diameters (at least 15 inches for #4 bar, 19 inches for
#5 bar), he can tie in the rest of this re-bar and continue the pour.
What an Civil Engineer will do to avoid Cold Joint at present instantly in the construction field:
Any Civil Engineer do not like cold
joint, but Cold Joint happens. If engineer know they have got another one coming
in the construction field, here are several things they can do,
---Try
to avoid cold joints in the middle of the wall, where the loads are high.
---Let
the re-bar run 2 to 3 feet out of the concrete at the joint so you can tie into
it when you continue the pour.
---If there is not already re-bar in
place where an engineer stop the pour, put some in before the concrete begins
to set.
To Be Continued...... ...... ...... ...... ...... ......
not bad...carry on my friend...
ReplyDeletethank you for your comment & suggestion, Mahir.
DeleteIf you have any curiosity on any topics/incidents which you want to know from me or you have anything that you want to share with me, Please tell me.
Decisions, Suggestions, Comments are always welcome.
Thanks for sharing...Keep it up.. (Y)
ReplyDeleteThank you for your support.
ReplyDeleteBest Regards,
Engr. Snehashish Bhattacharjee (Tushar).